Step by step: how a stretch ceiling is installed
Measuring, perimeter profiles, a made-to-measure membrane, tensioning and light fittings – usually in one day on site. What happens at each step and what to prepare before the crew arrives.
For clients preparing a room for installation and for contractors coordinating other trades on site.
A stretch ceiling comes together in two places: the membrane is made to measure off site, and on site the profiles are fitted and the membrane is tensioned. The installation itself usually takes one day in a typical room – but only if all decisions about lighting and services have been finalised beforehand.
Below are the steps in order, plus a short list of what is the client’s responsibility.
Five steps
Measuring and levelling. The room is measured and the lowest point of the slab is found. The ceiling level is set with a laser: the lowest point minus about 4 cm for a standard membrane, more for a backlit or acoustic one.
Perimeter profiles. Profiles that will hold the membrane are fixed to the walls along the marked line. Their length equals the perimeter of the room: a 4 × 5 m room needs 2 × (4 + 5) = 18 m of profile. In the same step, the support structures for light fittings, speakers or sensors are installed – once the membrane is tensioned, there is no access to them.
Made-to-measure membrane. Based on the measurements, the sheet is produced exactly for that room. If the shorter side exceeds the width of the given membrane – for some it is up to 5.4 m – the strips are welded together at the factory, and the seam position is agreed before production.
Tensioning. PVC film is installed hot: the room and the membrane are heated, the film becomes elastic, is fitted into the profiles and pulls taut and smooth as it cools. Technical fabric is fitted cold, without heating.
Light fittings and finishing. At the fitting positions the membrane is reinforced with a ring, and only then is the opening cut. Finally, the gap between the membrane and the wall is covered with a masking strip.
What to prepare before installation
The lighting decision: type and position of fittings, LED lines, and whether the whole sheet will be backlit. The build-up height depends on it.
Electrical cables run to the fitting points, and services above the ceiling completed and checked.
Wet trades finished – plastering, screeds, skim coats – and the walls next to the ceiling completed, since the profile and strip are added there after installation.
Clear access to the walls and a power socket. With a PVC membrane, also remove or cover anything sensitive to heat.
Frequently asked questions
How long does the whole process take?
On-site installation in a typical room usually takes one day. Before that come measuring and production of the made-to-measure membrane; the lead time for this part depends on the membrane type and any printing, so we give it with the quote.
Do I need to move out of the flat?
No. It is enough to move the furniture away from the walls and protect anything sensitive to heat. After a PVC film is installed, it is worth airing the room; fabric installed cold has practically no smell.
Can I book the installation during a renovation?
Yes, but as one of the last stages – after wet trades and services, before the final furnishing. We agree the details at the measuring visit; see stretch ceilings.